South Bridge Closing Information

The South Bridge will close at 10pm on Friday evening, September 17th, and re-open at 6am on Monday morning, September 20th.
The contractor will complete the overlay on both lanes, from the toll plaza to the center span of the bridge. In addition, they will complete the preparation for the overlay on the north side. Once all the deck panels are in place, they will finish the overlay on the center span and the north side. This work should start on Monday or Tuesday will be done during the usual 8pm 6am weekday closings. Keep in mind that the overlay work is weather sensitive.
The Bridge contractor will be putting in deck panels from early Sunday morning until 6 am Monday. Hopefully, they can complete the 12 remaining panels ( 4 are scheduled for tonight rain is forecast for tomorrow night) on Sunday. If not, the remaining panels will be done on Monday night.